- Sakaka project is located in Al Jouf province of the Kingdom of Saudi Arabia.
Contracted Capacity
- 300
Technology:
- Poly Crystalline Tracker System structure
Overview:
- Shuaibah project is located in Makkah al-Mukarramah province of the Kingdom of Saudi Arabia, 120 km south of Jeddah, with 900 MW contracted capacity.
Technology:
- Combined Cycle.
Overview:
- Shuaibah project is located in Makkah al-Mukarramah province of the Kingdom of Saudi Arabia.
Contracted Capacity:
- 900
Technology:
- Cogeneration Plant Steam Cycle
.
Overview:
- Marafiq project is located in the Eastern province of the Kingdom of Saudi Arabia.
Capacity (MW):
- 2743.6
Technology:
- Combined Cycle.
Overview:
- Rabigh-1 project is located in Makkah Al-Mukarramah.
Shareholders:
Saudi Electricity Company 20%
- ACWA Power 40%
- KEPCO 40%
Technology:
-Steam Power Plant
PPA Term:
- 20 years
Contracted Capacity:
- 1,204 MW AC
Overview:
- Riyadh PP11 project is located in Al Riyadh province of the Kingdom of Saudi Arabia.
Shareholders:
Saudi Electricity Company 50%
- Al-Jomaih 15%
- Engie 20%
- Sojitz 15%
Technology:
Combined Cycle.
PPA Term:
- 20 years
Contracted Capacity:
- 1,729.021MW
Overview:
- Qurayyah project is located in the Eastern province of the Kingdom of Saudi Arabia.
Shareholders:
- Saudi Electricity Company 50%
- ACWA Power 17.5%
- Samsung 17.5%
- MENA Infrastructure Fund 15%
Technology:
- Combined Cycle.
PPA Term:
- 20 years
Contracted Capacity:
- 3,927 MW
Overview:
- Rabigh 2 project is located in Makkah al-Mukarramah province of the Kingdom of Saudi Arabia.
.
Shareholders:
- Saudi Electricity Company 50%
- ACWA Power 37.5%
- Samsung 12.5%